Small Cabin

Small Cabin Forum
 - Forums - Register/Sign Up - Reply - Search - Statistics -

Small Cabin Forum / Cabin Construction / Workshop foundation advice
Author Message
karamazov
Member
# Posted: 26 Jan 2024 16:24
Reply 


Hi all,

I've been planning out a workshop that I'm going to build behind my garage for a while. I've settled on an overall size and design, but I am looking for some advice on what to do for the foundation.

Design for reference: https://imgur.com/311zfCk

It's a 14x32 with a gambrel roof and a loft. Currently I have it set up on 3 3-ply 2x8 beams for the skids and it's sitting on blocks (3x5 pattern). I'm planning to set up a compacted gravel pad slightly larger than the structure itself. To deal with wind I'm planning to use mobile home tie downs around the perimeter (I am not in a high wind or hurricane zone but just want to be safe).

Where I am the soil is pretty sandy for the first foot or two, and our frostline is something like 6".

Does anyone have experience with this kind of setup? Any advice? I also looked at piers. I have the equipment to do piers, just don't know if it's worth the effort and added cost in this case.

And yes I know that concrete slab might be the optimal choice, but a properly done slab is going to cost more than the entire rest of the structure according to the prices I've looked at. Plus I want flexibility to easily add plumbing later.

Brettny
Member
# Posted: 26 Jan 2024 16:35
Reply 


6in frost line I would dog down to below the frost and place 8x8x16 solid concrete blocks there. That's prety shallow frost line but with 3 skids you may never get a chance to re level if needed. I would skip the gravel pad, it's not really needed.

Have you thought about just doing 2 skids and doing 2x10 or 2x12 floor joists?

karamazov
Member
# Posted: 26 Jan 2024 16:42
Reply 


Thanks for the response!

I had considered it, but I really don't want my floors to be bouncy/springy. I also figured that distributing the weight across more blocks/larger surface area would reduce settling problems.

I had considered digging down a bit and packing gravel, placing blocks, mortaring them together, etc. If I'm going to dig down anyway though I figure maybe I'll just do piers.

One other thing I was trying to figure out is how close to the edge of the structure I need the skids to be. I've seen some people say that they need to be squarely under the load bearing walls, others say up to a foot of overhang is fine. Any thoughts there?

spencerin
Member
# Posted: 26 Jan 2024 20:05 - Edited by: spencerin
Reply 


Are you building the entire structure yourself? Or buying a pre-built 14' x 32' gambrel-style shed? I can tell you those types of sheds come on 2 runners/skids all the time, so the walls overhang the skids, without issue. That should answer your question about that.

Brett's foundation suggestion is probably the easiest and lowest cost. Why would you want to do piers? Are you talking about solid concrete piers, like sonotubes?

karamazov
Member
# Posted: 26 Jan 2024 20:25
Reply 


Quoting: spencerin
Are you building the entire structure yourself? Or buying a pre-built 14' x 32' gambrel-style shed? I can tell you those types of sheds come on 2 runners/skids all the time, so the walls overhang the skids, without issue. That should answer your question about that.

I looked at some Sturdi-bilt ones. To be honest I really wasn't impressed with their build quality. I can't justify paying $13k for something like that when I know I can build it far better for less.

For what it's worth all the ones I saw had 4 skids, with the outside ones pretty close to, but not exactly under, the walls.

Quoting: spencerin
Brett's foundation suggestion is probably the easiest and lowest cost. Why would you want to do piers? Are you talking about solid concrete piers, like sonotubes?

Yes I was originally planning to do rebar reinforced concrete piers w/footings dug down a couple feet.

gcrank1
Member
# Posted: 26 Jan 2024 20:42
Reply 


Fwiw, I was told the inner 'runners' were for carrying it on the delivery trailer/truck; the outer ones are where the building support needs to go.
That said, I can't think of a downside of 'blocking' the inner ones too except for the extra expense and difficulty in do it.

ICC
Member
# Posted: 26 Jan 2024 20:54
Reply 


Quoting: gcrank1
I can't think of a downside of 'blocking' the inner ones too except for the extra expense and difficulty in do it.



IF or when the building requires re-leveling those center supports will create difficulty.

Yes, I would want a very solid floor in my shop. I would also want the floor to be as level as possible and to stay that way. That makes it easier to build things that are square, level, plumb, and so on. I did spend a fair amount on a poured concrete monolith slab and foundation to get that though.

It is possible to use a roto-tiller to loosen the earth and dig down to a 12 to 18-inch depth. Then pour a concrete perimeter foundation, reinforced with rebar, using a portable mixer to mix your own sand, gravel, cement and water. Lay at least a single course of concrete block on that and you will have a better foundation than piers of any kind. That would be all tied together whereas piers are almost always individual units with each one free and able to move in different directions.

-izzy

karamazov
Member
# Posted: 26 Jan 2024 21:14
Reply 


Quoting: ICC
It is possible to use a roto-tiller to loosen the earth and dig down to a 12 to 18-inch depth. Then pour a concrete perimeter foundation, reinforced with rebar, using a portable mixer to mix your own sand, gravel, cement and water. Lay at least a single course of concrete block on that and you will have a better foundation than piers of any kind. That would be all tied together whereas piers are almost always individual units with each one free and able to move in different directions.

I appreciate the insight. I've had some others suggest doing a perimeter foundation. At one point I really liked the idea of doing a sort of conditioned crawlspace with a block perimeter. For DIY it seems a lot more doable than a mono slab.

I don't see a lot of those (or maybe any) down here in TX. Is that because they can have trouble with the expansive soils we have?

Brettny
Member
# Posted: 26 Jan 2024 22:13
Reply 


You definitely dont want to till up the soil then expect it to not move.

Can you get a concrete truck to your site? A concrete floor in a shop is very nice to work on and with 6in frost depth I would scrape off a few inches and make a form.

909
Member
# Posted: 26 Jan 2024 22:13 - Edited by: 909
Reply 


I did what you're planning, but used 18" x 18" x 3.5" footing blocks.

I also trucked in 7 loads of pit run ( road base ) on a tandem dump truck (14 - 16 tons per load ) totalling over 100 tonnes of material .

karamazov
Member
# Posted: 26 Jan 2024 22:34
Reply 


Quoting: 909
I did what you're planning, but used 18" x 18" x 3.5" footing blocks.

I also trucked in 7 loads of pit run ( road base ) on a tandem dump truck (14 - 16 tons per load ) totalling over 100 tonnes of material .

Ah well I'm interested to hear what your experience has been since! How has it held up?

You must have either gone deep with the gravel or have a much bigger pad because the gravel pit nearby told me I'd only need one load (about 15-16 yds)!

darz5150
Member
# Posted: 26 Jan 2024 23:08
Reply 


I put this 12 x 24 on this set up.
We did the outer perimeter with pre cast mafia blocks, then filled it with CA 6 unwashed rock and packed it with a track hoe. That was about 4 years ago. Did get some settling in one corner. But all in all it still is very solid.
12 x 24
12 x 24
Pre cast blocks
Pre cast blocks


ICC
Member
# Posted: 26 Jan 2024 23:30 - Edited by: ICC
Reply 


Quoting: Brettny
You definitely dont want to till up the soil then expect it to not move.


Sorry if I wasn't sufficiently explicit. The roto-tiller loosens the earth so it is easier to remove with a square-nose shovel. Remove the dirt and you have a trench much like you would have if dug with a backhoe. However, this way you don't need any heavy-duty equipment. The cost is more muscle power but fewer dollars from the budget.

-izzy

karamazov
Member
# Posted: 27 Jan 2024 14:29
Reply 


Quoting: darz5150
We did the outer perimeter with pre cast mafia blocks, then filled it with CA 6 unwashed rock and packed it with a track hoe. That was about 4 years ago. Did get some settling in one corner. But all in all it still is very solid.

Interesting, so you basically buried foundation blocks inside the gravel pad.

Are you concerned about moisture with the floor that close to the ground or is drainage good enough that it isn't a problem?

darz5150
Member
# Posted: 27 Jan 2024 16:44
Reply 


No. We Put the blocks on the outer perimeter.. then filled the void with the rock. Actually overfilled it and packed it. Then added more to bring it above the grade of the surrounding ground. You can kind of see in the first pic, the whole building and pad sits about 4 or 5 inches higher.
Don't seem to have any problem with drainage. The unwashed rock sets up like concrete.

darz5150
Member
# Posted: 27 Jan 2024 16:51
Reply 


Quoting: karamazov
Are you concerned about moisture with the floor that close to the ground

The floor was painted with water/stain proofing inside and out. The ends of the skids, I nailed hardware cloth on to them and buried it somewhat. So it still has some airflow underneath. It also has the foil bubble insulation between the joists and the floor.

spencerin
Member
# Posted: 28 Jan 2024 01:12
Reply 


I stand corrected. It looks like most of those 14' wide sheds are in fact on 4 skids/runners, not 2. FWIW.

Brettny
Member
# Posted: 28 Jan 2024 11:32
Reply 


That dosnt mean you need to support all 4.
20190818_1812251.jp.jpg
20190818_1812251.jp.jpg


spencerin
Member
# Posted: 28 Jan 2024 14:28
Reply 


But, isn't 14' too wide a span for most dimensional lumber? I would think support in the middle would still be needed.

karamazov
Member
# Posted: 29 Jan 2024 08:33
Reply 


Quoting: spencerin
But, isn't 14' too wide a span for most dimensional lumber? I would think support in the middle would still be needed.

The joist span calculator I used says you can go 14' with 2x10 SYP spaced at 2' on center, L/360 deflection. Then again I dont know how much sag our bounce the floor would end up having.

Brettny
Member
# Posted: 29 Jan 2024 09:54
Reply 


I wouldnt go anyless than 16in spacing. You have to think about how much deflection your going to get in 3/4 plywood.

909
Member
# Posted: 29 Jan 2024 10:49 - Edited by: 909
Reply 


I ended up using 2 x 10 PT spanning 10' spaced 16" on center .

3/4 SPF ply ontop. 1/2 PT ply on the bottom. R24 insulation. Resting on 6 x 6 PT beams about a foot from the ends.

karamazov
Member
# Posted: 29 Jan 2024 11:02
Reply 


Oh I'm definitely planning on 16", I was just saying that's what the calculator showed for 2x10.

909
Member
# Posted: 29 Jan 2024 15:35
Reply 


Quoting: karamazov
Ah well I'm interested to hear what your experience has been since! How has it held up?

You must have either gone deep with the gravel or have a much bigger pad because the gravel pit nearby told me I'd only need one load (about 15-16 yds)!


It's a brand new build. Perfect so far.


https://streamable.com/xw7ihf


We did an entire driveway plus the base for the cabin.







Your reply
Bold Style  Italic Style  Underlined Style  Thumbnail Image Link  Large Image Link  URL Link           :) ;) :-( :confused: More smilies...

» Username  » Password 
Only registered users can post here. Please enter your login/password details before posting a message, or register here first.